A BIM execution plan (BEP) is the document in which the appointed party on a BIM project explains how it will produce, check and deliver the information the client requires. ISO 19650 has two versions: a pre-appointment BEP for the tender and a post-appointment BEP for the contract. In Italian public contracts they are the offerta di gestione informativa (oGI) and the piano di gestione informativa (pGI).
The client's requirements say what it wants. The BEP says how the appointed party will deliver it, with which people, tools, rules and deadlines. If the requirements are vague, the BEP is where they get clarified. If the BEP is vague, every delivery turns into a negotiation.
What Italian law requires
Annex I.9 of Legislative Decree 36/2023, as amended by the corrective Legislative Decree 209/2024, sets out a sequence of three documents:
- the contracting authority attaches the capitolato informativo, Italy's Exchange Information Requirements, to the tender documents;
- in tenders awarded on the most economically advantageous tender criterion, the bidder submits an oGI in response to those requirements, drafted at the time of the bid;
- the winning bidder drafts the pGI on the basis of the oGI and submits it to the contracting authority after the contract is signed and before execution. If works start urgently, the authority can ask for it before signature. The plan can be updated during execution.
At acceptance or final testing, the appointed party then submits a specialist report on information modelling certifying that commitments were met. The text in force is on Normattiva.
The Code does not list the contents of the pGI. The Italian technical reference is UNI 11337-5, which defines information flows and project documents. Internationally it is ISO 19650-2, adopted in Italy as UNI EN ISO 19650-2, which describes the BEP before and after appointment. For readers outside Italy, everything below applies to an ISO 19650 BEP as well.
Pre-appointment and post-appointment BEP
People sometimes talk about a "tender pGI" and a "contract pGI". In the Code and in UNI 11337 they are two separate documents with different names.
| Pre-appointment BEP (oGI) | Post-appointment BEP (pGI) | |
|---|---|---|
| Written by | The bidder | The appointed party |
| When | During the tender, with the technical bid | After contract signature, before execution |
| Purpose | Show capability and method, be assessed | Set binding operating rules |
| People | Roles and profiles, often with CVs | Names, roles, responsibility per delivery |
| Deliveries | General strategy | Delivery plan per stage and information container |
| Rules | Commitments and proposed improvements | Coordinates, codes, naming, software versions fixed |
| Changes | Part of the bid | Can be updated during execution, with approval |
The point to remember: the post-appointment BEP is not a new bid. It cannot cut back what the tender BEP promised and the evaluation panel scored. It can detail it, correct what proved impractical with the client's agreement, and add the operating rules that were not needed in the tender.
How the BEP relates to the information requirements
The BEP answers the requirements section by section, so it pays to build it with the same table of contents. The client's information flow coordinator can then check each requirement without hunting for it. The sections of good requirements are described in 10 things to write in the capitolato informativo; the BEP has to give a concrete answer to each.
When the requirements are generic, for example "deliver in IFC" with no version, the BEP has to choose and state: version, MVD, property sets, export rules. The options are explained in our article on the IFC file format. A written, accepted choice is worth more than an ambiguous requirement.
What a BIM execution plan must contain
Organisation
- References: requirements, tender BEP, contract, standards applied, plan version and date.
- Model goals and uses confirmed per stage: coordination, quantities, design checking, 4D, operations.
- Delivery team with names and roles: BIM manager, BIM coordinator per discipline, BIM specialists, CDE manager, subcontractors and consultants.
- Responsibility matrix: for each delivery, who produces, who checks, who approves.
Deliveries
- Delivery plan per stage and discipline, with dates, information containers and required status. This is the Master Information Delivery Plan in ISO 19650 terms.
- Level of information need per element category and stage, in a matrix. The Italian LOD classes A to G of UNI 11337-4 help as a summary, but the matrix is what binds.
- Model-to-drawing matrix: which drawings derive from the model and which do not, and how a discrepancy is handled.
Production rules
- Federation strategy: how models are split by discipline, building, zone and level.
- Coordinates and units: shared reference point, coordinate reference system, orientation, units.
- Coding and naming of files, objects, types and levels, with examples.
- Classification system and the fields where it is recorded.
- Software and versions per discipline, exchange formats and the interoperability tests to run before the first delivery.
Environment and checks
- CDE: platform, folder structure, container states, approval workflows, permissions, synchronisation with the client's environment.
- Coordination: clash detection frequency, clash matrix, issue management in BCF, meetings.
- Quality checks: checking rules, preferably automated and written in IDS, tolerances, reports.
- As-built and operations: content of the final model, facility management attributes, specialist report at acceptance.
- Change management: how the BEP is updated, who approves it, how versions are tracked.
Acceptance checklist
If you are the client, before accepting a BEP check that:
- every requirement has an answer you can find;
- no tender commitment has been reduced without agreement;
- people have names, not just roles;
- the delivery plan has dates and contents, not just stages;
- coordinates, units and coding are written with examples;
- IFC version and MVD are stated;
- quality checks are described with rules, frequencies and tolerances;
- the model-to-drawing matrix is there;
- it is clear what is handed over at acceptance and with which attributes;
- the procedure for updating the plan is defined.
Mistakes we see most often
- Post-appointment BEP copied from the tender BEP with only the title changed: generic promises remain and operating rules are missing.
- A hundred-page document that transcribes the standards. A useful BEP is short and points to annexes: matrices, naming examples, IDS files.
- Roles without people, or one BIM manager named on too many projects at once.
- No interoperability test before the first delivery: coordinate and export problems surface at the first federated model.
- A plan never updated: the site changes, the BEP stays as it was six months earlier and nobody reads it.
- Subcontractors left out: whoever models MEP in detailed design does not know the rules to follow.
BIMON's experience
On the Doha Metro Red Line North we supported Italferr in the BIM management and coordination of seven underground stations: discipline models were integrated into one federated model for clash management, and the final and detailed design drawings were extracted from the model. That is the kind of project where the federation strategy and the model-to-drawing matrix have to be written before modelling starts. On The Factory in Manchester, with Ryder Architecture, design issues were tracked and resolved before construction using Navisworks and BIM Track: a coordination procedure the BEP should describe with frequencies and owners. For Mexico City Airport we built, at tender stage for Astaldi, the multidisciplinary BIM model of the CITT building, with 4D and 5D simulations that helped optimise the solutions in the bid. That is the pre-appointment side of the process, where the method has to convince before the contract.
What BIMON does
For contractors and designers we write the tender BEP and the post-appointment BEP, and make them work on the project through Project BIM Management. For clients we review the BEPs they receive against their requirements through our BIM management service. The definitions of oGI and pGI are in our glossary. To have a plan reviewed or to set up a new one, contact us. This article is for information only and is not legal advice.